G
GJB
Hi,
I am currently running a single W2K/EX2K forest/domain with 2 c DC/GC. There
are 6 x W2K/EX2K cluster in this org.
I am intending to upgrade to W2K3/EX2K3 and to all new hardware in the
following way.:-
Run mangled attributes script
Run W2K3 forest/Domain prep on current schema master
Run EX2K3 forest/Domain prep current schema master
Promote 2 new W2K3 servers to DCs and xfer the roles across
Demote and retire existing DCs.
Build 6 x new W2K3/EX2K3 clusters and move mailboxes
Remove/Retire Existing clusters
Could anyone who has already achieved this possibly comment with any tips/
gotchas
Thanks,
GJb
I am currently running a single W2K/EX2K forest/domain with 2 c DC/GC. There
are 6 x W2K/EX2K cluster in this org.
I am intending to upgrade to W2K3/EX2K3 and to all new hardware in the
following way.:-
Run mangled attributes script
Run W2K3 forest/Domain prep on current schema master
Run EX2K3 forest/Domain prep current schema master
Promote 2 new W2K3 servers to DCs and xfer the roles across
Demote and retire existing DCs.
Build 6 x new W2K3/EX2K3 clusters and move mailboxes
Remove/Retire Existing clusters
Could anyone who has already achieved this possibly comment with any tips/
gotchas
Thanks,
GJb