G
Guest
My data set looks like:
Position Start Time Duration Start Time Duration
Cook 7 17
Server 11 3 5
5
I want a chart that looks like:
Cook *************************************
Server ******* ************
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I seem to be able to only get one series to show (the cook, not the server)
- and I'm not sure how I will be able to create the "broken" bar for the two
separate server shifts.
Thanks for any help someone can give!
Position Start Time Duration Start Time Duration
Cook 7 17
Server 11 3 5
5
I want a chart that looks like:
Cook *************************************
Server ******* ************
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I seem to be able to only get one series to show (the cook, not the server)
- and I'm not sure how I will be able to create the "broken" bar for the two
separate server shifts.
Thanks for any help someone can give!