G Guest Nov 17, 2007 #1 Have Exch 2003 Srvr. Staff need to schedule meeting beyond 60 days. Not able to see the appointments. How to fix?
Have Exch 2003 Srvr. Staff need to schedule meeting beyond 60 days. Not able to see the appointments. How to fix?
M Milly Staples [MVP - Outlook] Nov 17, 2007 #2 Increase your free/busy time period from the default 2 months to 12 months. This needs to be done on each user's machine. -- Milly Staples [MVP - Outlook] Post all replies to the group to keep the discussion intact. After furious head scratching, Mbailey asked: | Have Exch 2003 Srvr. Staff need to schedule meeting beyond 60 days. | Not able to see the appointments. How to fix?
Increase your free/busy time period from the default 2 months to 12 months. This needs to be done on each user's machine. -- Milly Staples [MVP - Outlook] Post all replies to the group to keep the discussion intact. After furious head scratching, Mbailey asked: | Have Exch 2003 Srvr. Staff need to schedule meeting beyond 60 days. | Not able to see the appointments. How to fix?