Hi,

Trying to format a chart so that only the 5 working days of the week are
displayed on the x axis. The source data only has the five days (e.g.
05/09/2005 down to 09/09/2005 and then on to 12/09/2005 down to 16/09/2005
etc etc) So I have missed out the weekend dates.

When I create the line chart however, the weekend dates appear automatically
and just show no point on the chart, therefore there is a longer line between
Fridays and Mondays!!

Hope this makes sense.

Does anyone have any ideas on how to change this? I have tried looking at
Tools-options-chart and cannot seem to turn this feature off.

Thanks
 
Hi,

Try right clicking chart and chose Chart Options. On the axes tab change
the chart to category instead of automatic or time series.

Cheers
Andy
 
That's got it! Thanks Andy.



Andy Pope said:
Hi,

Try right clicking chart and chose Chart Options. On the axes tab change
the chart to category instead of automatic or time series.