Last day of task showing overallocated

  • Thread starter Thread starter Guest
  • Start date Start date
G

Guest

I have a resource permitted to work up to 8 hours per day. I've assigned him
a task that lasts over 10 days. On the last day of that task, even though
he's only working 8 hours, Project is relfecting those 8 hours in red (as in
'overallocated'). It doesn't have anything to do with date - if I shift the
task to start earlier or later it still shows red.

Any ideas? Thanks!
 