In a GANTT, how do I get diff projects to start later on chart

  • Thread starter Thread starter Guest
  • Start date Start date
G

Guest

I want to show a flow of projects, by date. When one stops, the other starts
or maybe the next starts a couple days before. How do you set up the GANTT
to show the stepping effect. Currently all I can get it to do is all
projects start at the same time. Thanks for the help
 
A project bar in a Gantt chart is the stacked bar defined by a start date and a
duration. To make a bar start later, give it a later start date. You should be able
to use formulas to relate a later start to the earlier starting date and duration of
another bar.

These articles might be of assistance:

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=343
http://peltiertech.com/Excel/Charts/GanttChart.html

- Jon
-------
Jon Peltier, Microsoft Excel MVP
Peltier Technical Services
Tutorials and Custom Solutions
http://PeltierTech.com/