R
Roy
At work we run 4 production Teams; Team 1 thru Team 4. Each Team is
assigned a production schedule every week. There are a total of 23 possible
production schedules, each one different.
Every week the various production schedule number (1 - 23) is recorded in a
column under the Team's number. The sequence of the schedules is erratic,
that is the same team could have the same schedule in two consecutive weeks;
or could go from schedule 8 to schedule 15. At the leftmost column is the
date.
What I need to do is, on another worksheet, enter a row of numbers 1 - 23.
Under each number I need a formula that will look at all the various
production schedules, in total, and tell me how many weeks it's been since
that particular schedule was run. An example is below. It does not need to
be by team, just the weeks since a particular schedule was run.
1 2 3 4
10/04/03 15 22 14 9
10/11/03 5 11 22 17
10/18/03 4 6 21 23
10/25/03 7 12 21 19
Thanks in anticipation
assigned a production schedule every week. There are a total of 23 possible
production schedules, each one different.
Every week the various production schedule number (1 - 23) is recorded in a
column under the Team's number. The sequence of the schedules is erratic,
that is the same team could have the same schedule in two consecutive weeks;
or could go from schedule 8 to schedule 15. At the leftmost column is the
date.
What I need to do is, on another worksheet, enter a row of numbers 1 - 23.
Under each number I need a formula that will look at all the various
production schedules, in total, and tell me how many weeks it's been since
that particular schedule was run. An example is below. It does not need to
be by team, just the weeks since a particular schedule was run.
1 2 3 4
10/04/03 15 22 14 9
10/11/03 5 11 22 17
10/18/03 4 6 21 23
10/25/03 7 12 21 19
Thanks in anticipation