Friday as weekend in Workday Function

  • Thread starter Thread starter Naushad
  • Start date Start date
This isn't clear, what are the weekend days?

Fri & Sun, Fri & sat or just Friday

Mike
 
How can i change weekend from saturday & Sunday to Friday for a workday
function

What do you mean by that?

Is your weekend only Friday?
Friday and Saturday?
Friday, Saturday and Sunday?

--ron
 
Instead of
=WORKDAY(A1,B1)
try
=WORKDAY(A1+1,B1)-1

where A1 contains the Start Date and B1 the Number of Days...

Not sure how this will work if you add Holidays and the holiday falls on Fri
or Sun...
Can you pl. test and let us know?
 
Hi,

your solution takes Fri & Sat as weekends. If you can recheck and find
solution for Friday as weekend only. Thanks
 
Hi,

it is a good site, but I couldn't find the solution of my problem. I need to
find the end date by adding number of days to a start date and taking only
Friday as weekly hoilday.
 