estimates

  • Thread starter Thread starter Guest
  • Start date Start date
G

Guest

I am completing an estimate on a recent job that i have done. the last three
columns I have are Amount (which is the amount of money a company has payed
us), % completed (which is the amount of work that my company has completed),
and finally the balance (which is the amount that I should get from the
percent, and the amount of money I have recieved. I am trying to figure out
how to get the balance with the other two information I have in hand without
manually solving. please help.
 
Hi

We are missing one value - the total contract value

Formula would be
=(Contract_value*%complete)-Amount_Paid
 
Back
Top